[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899765":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899765,582,2,"多选题","下列各种定额中，定额水平为社会平均水平的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工定额",false,{"key":16,"text":17,"correct":18},"B","预算定额",true,{"key":20,"text":21,"correct":18},"C","概算定额",{"key":23,"text":24,"correct":18},"D","概算指标",{"key":26,"text":27,"correct":18},"E","投资估算指标","BCDE","2020版教材P40 选项A，施工定额的定额水平为社会平均先进水平。 表格2.1.1",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]