[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899761":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899761,582,2,"多选题","下列关于工程量清单计价程序和方法的说法中，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","编制建设工程造价的基本过程只有工程量计算",false,{"key":16,"text":17,"correct":18},"B","工程量清单计价要历经工程量清单编制和工程量清单应用两个阶段",true,{"key":20,"text":21,"correct":14},"C","工程量清单在发承包阶段的应用主要是用来编制招标控制价、投标报价和工程计量、工程结算和工程计价纠纷的解决",{"key":23,"text":24,"correct":14},"D","招标控制价和投标报价的编制依据相同",{"key":26,"text":27,"correct":18},"E","综合单价由人工费、材料和工程设备费、施工机具使用费、企业管理费、利润及一，定范围内的风险费用组成","BE","2020版教材P38~39 工程量清单在发承包阶段的应用包括招标控制价和投标报价的编制，工程量计算、工程结算等属于施工阶段的应用。 投标报价的编制依据包括企业定额，招标控制价的编制依据不包括企业定额。 工程量清单计价的过程可以分为两个阶段，即工程量清单的编制和工程量清单的应用两个阶段，",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]