[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899759":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899759,582,2,"多选题","工程量清单计价中，分部分项工程的综合单价由完成规定计量单位工程量清单项目所需（ ）等费用组成。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","人工费、材料费、机具使用费",true,{"key":16,"text":17,"correct":14},"B","管理费",{"key":19,"text":20,"correct":21},"C","临时设施费",false,{"key":23,"text":24,"correct":14},"D","利润",{"key":26,"text":27,"correct":21},"E","税金","ABD","2020版教材P35 清单综合单价中除包括人工、材料、机具使用费用外，还包括企业管理费、利润和风险因素；全费用综合单价中除包括人工、材料、机具使用费外，还包括企业管理费、利润、规费和税金。@##",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]