[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899758":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899758,582,2,"多选题","世界银行、国际咨询工程师联合会规定工程项目总建设成本包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目直接建设成本",true,{"key":16,"text":17,"correct":14},"B","项目间接建设成本",{"key":19,"text":20,"correct":21},"C","预备费",false,{"key":23,"text":24,"correct":14},"D","应急费",{"key":26,"text":27,"correct":14},"E","建设成本上升费","ABDE","2020版教材P2 世界银行、国际咨询工程师联合会对项目的总建设成本（相当于我国的工程造价）作了统一规定，工程项目总建设成本包括直接建设成本、间接建设成本、应急费和建设成本上升费等。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]