[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899725":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899725,582,2,"多选题","下列各费用项目中属于措施费的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","财务费",false,{"key":16,"text":17,"correct":18},"B","施工降水费",true,{"key":20,"text":21,"correct":14},"C","管理人员工资",{"key":23,"text":24,"correct":18},"D","已完工程及设备保护费",{"key":26,"text":27,"correct":14},"E","广告费","BD","2020版教材P15 措施费包括：①安全文明施工费；②夜间施工增加费；③非夜间施工照明费；④二次搬运费；⑤冬雨季施工增加费；⑥地上及地下设施、建筑物的临时保护设施费；⑦已完工程及设备保护费：⑧脚手架费；⑨混凝土模板及支架（撑）费；⑩垂直运输费；（11）超高施工增加费；（12）大型机械设备进出场及安拆费；（13）施工排水、降水费；（14）其他。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]