[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899702":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899702,582,2,"多选题","某建设项目的进口设备采用装运港船上交货价，则买方的责任有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","负责租船并将设备装上船只",false,{"key":16,"text":17,"correct":18},"B","负责租船或订舱，支付运费",true,{"key":20,"text":21,"correct":18},"C","负担货物在装运港越过船舷后的各种费用以及货物灭失或损坏的一切风险",{"key":23,"text":24,"correct":18},"D","办理在目的港的收货手续",{"key":26,"text":27,"correct":14},"E","办理出口手续","BCD","2020版教材P6 FOB意为装运港船上交货，亦称为离岸价格。在采用装运港船上交货价时，买方的基本义务有：负责租船订舱，按时派船到合同约定的装运港接运货物，支付运费，并将船期、船名及装船地点及时通知卖方；负担货物在装运港装上船后的各种费用以及货物灭失或损坏的一切风险；负责获取进口许可证或其他官方文件，以及办理货物入境手续；受领卖方提供的各种单证，按合同规定支付货款。 办理出口手续以及将设备装上船只均属于卖方的基本义务。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]