[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899688":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899688,582,2,"多选题","根据现行规定，合同中没有适用或类似于变更工程的价格，其工程变更价款的处理原则是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","由工程师提出适当的变更价格，报业主批准执行",false,{"key":16,"text":17,"correct":18},"B","由承包方提出适当的变更价格，经工程师确认后执行",true,{"key":20,"text":21,"correct":14},"C","当工程师与承包方对变更价格意见不一致时，由工程师确认其认为合适的价格",{"key":23,"text":24,"correct":18},"D","当工程师与承包方对变更价格意见不一致时，可以由造价管理部门调解",{"key":26,"text":27,"correct":14},"E","当业主与承包方对变更价格意见不一致时，由造价管理部门裁定","BD","根据现行规定，合同中没有适用或类似于变更工程的价格，其工程变更价款的处理原则是由承包方提出适当的变更价格，经工程师确认后执行。当工程师与承包方对变更价格意见不一致时，可以由造价管理部门调解。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]