[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899686":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899686,582,2,"多选题","根据《标准施工招标文件》(2007)版，承包人有可能同时获得工期和费用补偿的事件有（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发包方延期提供施工图纸",true,{"key":16,"text":17,"correct":18},"B","因不可抗力造成的工期延误",false,{"key":20,"text":21,"correct":14},"C","甲供设备未按时进场导致停工",{"key":23,"text":24,"correct":14},"D","监理对覆盖的隐藏工程重新检查且结果合格",{"key":26,"text":27,"correct":14},"E","施工中发现文物古迹","ACDE","引起承包人索赔的事件以及可能得到的合理补偿内容如下表所示。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]