[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899681":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899681,582,2,"多选题","根据《标准施工招标文件》（2007 版）通用合同条款，承包人可能同时获得工期和费用补偿、但不能获得利润补偿的索赔事件有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","迟延提供施工场地",false,{"key":16,"text":17,"correct":18},"B","发包人更换其提供的不合格设备",true,{"key":20,"text":21,"correct":14},"C","发包人负责的材料推迟提供",{"key":23,"text":24,"correct":14},"D","监理人指令错误",{"key":26,"text":27,"correct":18},"E","施工中发现文物","BE","选项 A，迟延提供施工场地，可以获得工期、费用和利润补偿；选项 B，发包人更换其提供的不合格设备，可以获得工期和费用补偿，不能获得利润补偿；选项 C，发包人负责的材料延迟提供，可以获得工期、费用和利润补偿；选项 D：监理人指令错误，可以获得工期和费用补偿，以及利润；选项 E，施工中发现文物，可以获得工期和费用补偿，不能获得利润补偿。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]