[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899673":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899673,582,2,"多选题","关于工程计量，下列说法错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程计量可选择按月或按工程形象进度分段计量",false,{"key":16,"text":17,"correct":18},"B","承包人原因造成的返工工程量应予计量",true,{"key":20,"text":21,"correct":14},"C","单价合同工程量必须以承包人完成合同工程应予计量的工程量确定",{"key":23,"text":24,"correct":18},"D","总价合同约定的项目计量应以实际完成的工程量为依据",{"key":26,"text":27,"correct":14},"E","工程计量可以依据工程量清单及说明","BD","承包人原因造成的返工工程量，不予计量。除按照工程变更规定引起的工程量增减外，总价项目的工程量是承包人用于结算的最终工程量。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]