[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899672":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899672,582,2,"多选题","下列关于国际性招标的说法正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","如果投标人未经资格预审，则评标的过程中应对所有的投标人进行资格定审",false,{"key":16,"text":17,"correct":18},"B","采用“两个信封制度”的，技术上不符合要求的标书则第二个信封不再开启",true,{"key":20,"text":21,"correct":18},"C","在谈判过程中，发包人不得要求投标人承担额外的工作",{"key":23,"text":24,"correct":14},"D","标价由直接费用、间接费用以及利润组成",{"key":26,"text":27,"correct":18},"E","凡采购大而复杂的工程宜采用资格预审","BCE","A 如果投标人未经资格预审，则应对评标价最低的投标人进行资格定审；D 标价由直接费用、间接费用、利润和风险费组成。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]