[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899659":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899659,582,2,"多选题","《招标施工招标文件》（2007 版），下列有关施工招标的说法中正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","当进行资格预审时，招标文件中应包括投标邀请书",true,{"key":16,"text":17,"correct":14},"B","投标准备时间最短不得少于20 天",{"key":19,"text":20,"correct":21},"C","投标人对招标文件有疑问时，应在规定时间内以电话、电报等方式要求招标人澄清",false,{"key":23,"text":24,"correct":21},"D","按照规定应编制招标控制价的项目，其控制价应在开标时一并公布",{"key":26,"text":27,"correct":14},"E","详细评审可选择经评审的最低投标价法和综合评估法","ABE","选项 C 错误，投标人应在规定的时间前以书面形式（包括信函.电报.传真等可以有形地表现所载内容的形式），要求招标人对招标文件予以澄清；选项 D 错误，按照规定应编制招标控制价的项目，其控制价应在招标时一并公布。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]