[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899629":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899629,582,2,"多选题","下列对工人工作时间中基本工作时间的理解正确的是（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","基本工作时间与辅助工作时间之和构成了有效工作时间",false,{"key":16,"text":17,"correct":18},"B","基本工作时间的长短与工作量大小成正比",true,{"key":20,"text":21,"correct":14},"C","基本工作时间是在正常额定负荷状态下的工作时间",{"key":23,"text":24,"correct":18},"D","基本工作时间可以改变产品的外形、结构或性质",{"key":26,"text":27,"correct":14},"E","基本工作时间中包括由施工工艺特点引起的工作时间所必须的时间","BD","有效工作时间包含基本工作时间、辅助工作时间、准备与结束工作时间；基本工作时间和辅助工作时间组成了工序作业时间；基本工作时间的长短和工作量大小成正比；不可避免的中断时间是由于施工工艺特点引起的工作中断所必须的时间。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]