[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899626":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899626,582,2,"多选题","关于暂估价的计算和填写，下列说法中正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","暂估价数量和拟用项目应结合工程量清单中的“暂估价表”予以补充说明",true,{"key":16,"text":17,"correct":18},"B","材料暂估价应由招标人填写暂估单价，无须指出拟用于哪些清单项目",false,{"key":20,"text":21,"correct":18},"C","工程设备暂估价不应纳入分部分项工程综合单价",{"key":23,"text":24,"correct":14},"D","专业工程暂估价应分不同专业，列出明细表",{"key":26,"text":27,"correct":14},"E","专业工程暂估价由招标人填写，并计入投标总价","ADE","材料暂估单价及调整表由招标人填写“暂估单价”，并在备注栏说明暂估价的材料.工程设备拟用在哪些清单项目上，投标人应将上述材料.工程设备暂估价计入工程量清单综合单价报价中。工程设备暂估价应纳入分部分项工程综合单价。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]