[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899575":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899575,582,2,"多选题","(2018年)承包人提交的已完工程进度款支付申请中，应计入本周期完成合同价款中的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","本周期已完成单价项目的金额",true,{"key":16,"text":17,"correct":14},"B","本周期应支付的总价项目的金额",{"key":19,"text":20,"correct":21},"C","本周期应扣回的预付款",false,{"key":23,"text":24,"correct":14},"D","本周期应支付的安全文明施工费",{"key":26,"text":27,"correct":14},"E","本周期完成的计日工价款","ABDE","本周期合计完成的合同价款，其中包括：①本周期已完成单价项目的金额；②本周期应支付的总价项目的金额；③本周期已完成的计日工价款；④本周期应支付的安全文明施工费；⑤本周期应增加的金额。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]