[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899560":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899560,582,2,"多选题","(2013年)下列事件的发生，已经或将造成工期延误，则按照《标准施工招标文件》中相关合同条件，可以获得工期补偿的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","监理人发出错误指令",true,{"key":16,"text":17,"correct":18},"B","监理人对已覆盖的隐蔽工程要求重新检查且检查结果不合格",false,{"key":20,"text":21,"correct":18},"C","承包人的设备故障",{"key":23,"text":24,"correct":14},"D","发包人提供工程设备不合格",{"key":26,"text":27,"correct":14},"E","异常恶劣的气候条件","ADE","监理人指令迟延或错误，可赔偿工期和费用；监理人对已覆盖的隐蔽工程要求重新检查且检查结果不合格，不赔偿；承包人的设备故障，不赔偿；发包人提供工程设备不合格，可赔偿工期、费用和利润；异常恶劣的天气条件，可赔偿工期。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]