[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899557":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899557,582,2,"多选题","(2016年)根据《标准施工招标文件》（2007年版）通用合同条款，承包人可能同时获得工期和费用补偿，但不能获得利润补偿的索赔事件有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","延迟提供施工场地",false,{"key":16,"text":17,"correct":18},"B","施工遇到不利物资条件",true,{"key":20,"text":21,"correct":14},"C","发包人负责的材料延迟提供",{"key":23,"text":24,"correct":14},"D","监理人指令错误",{"key":26,"text":27,"correct":18},"E","施工中发现文物","BE","《标准施工招标文件》 中承包人的索 赔事件及可补偿内容。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]