[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899539":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899539,582,2,"多选题","(2015年)根据《建设工程工程量清单计价规范》( GB 50500-2013)，在其他项目清单中，应由投标人自主确定价格的有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","暂列金额",false,{"key":16,"text":17,"correct":14},"B","专业工程暂估价",{"key":19,"text":20,"correct":14},"C","材料暂估单价",{"key":22,"text":23,"correct":24},"D","计日工单价",true,{"key":26,"text":27,"correct":24},"E","总承包服务费","DE","该题主要考察的是：其他项目清单 “计日工应按照招标人提供的其他项目清单列出的项目和估算的数量，自主确定各项综合单价并计算费用。总承包服务费应根据招标人在招标文件中列出的分包专业工程内容和供应材料、设备情况，按照招标人提出的协调、配合与服务要求和施工现场管理需要自主确定。”暂列金额、暂估价由招标人确定。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]