[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899534":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899534,582,2,"多选题","(2016年)关于招标分部分项工程量清单的项目特征描述，应遵循的编制原则有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","按专业工程量计算规范附录的规定，结合拟建工程实际描述",true,{"key":16,"text":17,"correct":14},"B","其他独有特征，由清单编制人视项目具体情况确定",{"key":19,"text":20,"correct":14},"C","要满足确定综合单价的需要",{"key":22,"text":23,"correct":24},"D","应详细描述分部分项工程的施工工艺和方法",false,{"key":26,"text":27,"correct":14},"E","对于采用标准图集的项目，可直接描述为“详见##图集”","ABCE","本题考查的是招标工程量清单的编制。选项D错误，在编制分部分项工程量清单时，工作内容通常无需描述；选项E错误，若采用标准图集或施工图纸能够全部或部分满足项目特征描述的要求，项目特征描述可直接采用详见XX图集或XX图号的方式。对不能满足现目特征描述要求的部分，仍应用文宇描述。参见教材P178。@##",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]