[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899533":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899533,582,2,"多选题","(2018年)关于工程施工项目最高投标限价编制的注意事项,下列说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","未釆用工程造价管理机关发布的工程造价信息时,应予以说明",true,{"key":16,"text":17,"correct":18},"B","施工机械设备的选型应本着经济实用、平均有效的原则确定",false,{"key":20,"text":21,"correct":18},"C","暂估价中的材料单价应通过市场调查确定",{"key":23,"text":24,"correct":14},"D","不可竞争措施项目费应按国家有关规定计算",{"key":26,"text":27,"correct":14},"E","竞争性措施项目费应依据经专家论证确认的施工组织设计或施工方案","ADE","施工机械设备的选型本着经济实用、先进高效的原则确定，B错误；采用的材料价格应是工程造价管理机构通过工程造价信息发布的材料价格，工程造价信息未发布材料单价的材料，其材料价格应通过市场调查确定，C错误。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]