[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899530":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899530,582,2,"多选题","(2015年)根据《建设工程工程量清单计价规》(GE50500-2010)，招标控制价中综合单价中应考虑的风险因素包括()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目管理的复杂性",true,{"key":16,"text":17,"correct":14},"B","项目的技术难度",{"key":19,"text":20,"correct":21},"C","人工单价的市场变化",false,{"key":23,"text":24,"correct":14},"D","材料价格的市场风险",{"key":26,"text":27,"correct":21},"E","税金、规费的政策变化","ABD","该题主要考察的是：招标控制价的编制 “应考虑的风险因素：(1)技术难度较大和管理复杂的项目，可考虑一定的风险费用纳入到综合单价中； (2)工程设备、材料价格的市场风险，考虑一定率值的风险费用，纳入到综合单价中； (3)税金、规费等法律、法规、规章和政策变化风险和人工单价等风险费用，不应纳入综合单价。”",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]