[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899528":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899528,582,2,"多选题","(2015年)关于招标工程量清单的编制，下列说法正确的是( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","若采用标准图集能够全部满足项目特征描进的要求，项目特征描进可直接采用“详见xx图”的格式",true,{"key":16,"text":17,"correct":14},"B","措施项目清单的编制需考虑工程本身、水文、气象、环境、安全等多种因素",{"key":19,"text":20,"correct":21},"C","以“项”为计量单位的专业工程暂估价一般应包括管理费、规费、利润、税金等",false,{"key":23,"text":24,"correct":14},"D","工程量清单总说明应对工程概况、工程招标及分包范围、工程质量要求等进行描进",{"key":26,"text":27,"correct":14},"E","工程量清单编制依据包括设计文件、招标文件、施工现场情况、常规施工方案等","ABDE","该题主要考察的是：招标工程量清单的编制，“选项C错误，以“项”为计量单位结出的专业工程暂估价一般应是综合暂估价，即应当包括扣除规费、税金以外的管理费、利润等。”",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]