[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899526":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899526,582,2,"多选题","(2018年)在编制单位建筑工程施工图预算时,一般应计入综合取定的措施项目费的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工降水费用",false,{"key":16,"text":17,"correct":18},"B","冬雨季施工增加费",true,{"key":20,"text":21,"correct":18},"C","夜间施工增加费",{"key":23,"text":24,"correct":14},"D","模板费用",{"key":26,"text":27,"correct":14},"E","脚手架费用","BC","综合取定的措施项目费包括夜间施工增加费，非夜间施工照明费，二次搬运费，冬雨季施工增加费，地上、地下设施和建筑物的临时保护设施费、已完工程及设备保护费等。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]