[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899519":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899519,582,2,"多选题","(2013年)某建设项目由厂房、办公楼、宿舍等单项工程组成，则可包含在各单项工程综合概算中的内容有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","机械设备及安装工程概算",true,{"key":16,"text":17,"correct":14},"B","电气设备及安装工程概算",{"key":19,"text":20,"correct":21},"C","工程建设其他费用概算",false,{"key":23,"text":24,"correct":14},"D","特殊构筑物工程概算",{"key":26,"text":27,"correct":21},"E","流动资金概算","ABD","单项工程综合概算包括单位建筑工程概算和单位设备及安装工程概算，其中单位建筑工程概算包括一般土建工程概算，给排水、采暖工程概算，通风、空调工程概算，电气照明工程概算，弱电工程概算，特殊构筑物工程概算等。单位设备及安装工程概算包括机械设备及安装工程概算，电气设备及安装工程概算，热力设备及安装工程概算，工具、器具及生产家具购置费用概算等。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]