[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899506":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899506,582,2,"多选题","(2014年)建设项目工程造价指数是由（）指数综合得到的",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","设备、工器具价格指数",true,{"key":16,"text":17,"correct":18},"B","人工费价格指数",false,{"key":20,"text":21,"correct":14},"C","建筑安装工程造价指数",{"key":23,"text":24,"correct":18},"D","材料价格指数",{"key":26,"text":27,"correct":14},"E","工程建设其它费用指数","ACE","建设项目或单项工程造价指数。该指数是由设备、工器具指数、建筑安装工程造价指数、工程建设其他费用指数综合得到的。它也属于总指数，并且与建筑安装工程造价指数类似，一般也用平均数指数的形式来表示。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]