[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899500":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899500,582,2,"多选题","(2018年)关于概算定额与预算定额，下列说法正确的有（ ）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","概算定额的主要内容、主要方式及基本使用方法与预算定额相同",true,{"key":16,"text":17,"correct":14},"B","概算定额与预算定额的不同之处，在于项目划分和综合扩大程度上的差异",{"key":19,"text":20,"correct":21},"C","概算定额是确定概算指标中各种消耗量的依据",false,{"key":23,"text":24,"correct":21},"D","概算定额与预算定额之间的水平差一般在10%左右",{"key":26,"text":27,"correct":14},"E","概算定额项目可以按工程结构划分，也可以按工程部位划分","ABE","选项C 错误，概算指标中各种消耗量指标的确定，主要来自各种预算或结算资料。选项D 错误，概算定额与预算定额之间的水平差一般在5%左右。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]