[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899496":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899496,582,2,"多选题","(2013年)预算定额中人工、材料、机械台班消耗量的确定方法包括()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","以施工定额为基础确定",true,{"key":16,"text":17,"correct":14},"B","以现场观察测定资料为基础计算",{"key":19,"text":20,"correct":21},"C","以工程量计算规则为依据计算",false,{"key":23,"text":24,"correct":21},"D","以各类费用定额为基础确定",{"key":26,"text":27,"correct":21},"E","以工程结算资料为依据计算","AB","预算定额中人工、材料、机械台班消耗水平，需要根据劳动定额或施工定额取定；人工的工日数可以有两种确定方法，一种是以劳动定额为基础确定；另一种是以现场观察测定资料为基础计算。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]