[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899494":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899494,582,2,"多选题","（2019年真题）下列人工、材料、机械台班的消耗，应计入定额消耗量的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","准备与结束工作时间",true,{"key":16,"text":17,"correct":18},"B","施工本身原因造成的工人停工时间",false,{"key":20,"text":21,"correct":14},"C","措施性材料的合理消耗量",{"key":23,"text":24,"correct":14},"D","不可避免的施工废料",{"key":26,"text":27,"correct":18},"E","低负荷下的机械工作时间","ACD","P54-60 施工本身原因造成的工人停工时间和低负荷下的机械工作时间属于损失时间，不应计入定额消耗量。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]