[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899487":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899487,582,2,"多选题","(2013年)为保证写实记录法数据的可靠性，写实记录延续时间的确定，应满足的要求有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","算术平均值精确度",false,{"key":16,"text":17,"correct":18},"B","被测定个人或小组的最低数量",true,{"key":20,"text":21,"correct":14},"C","测定的数列的稳定系数",{"key":23,"text":24,"correct":18},"D","测定总延续时间的最小值",{"key":26,"text":27,"correct":18},"E","测定完成产品的最低次数","BDE","写实记录法应满足的要求：被测定个人或小组的最低数量、测定总延续时间的最小值、测定完成产品的最低次数。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]