[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899478":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899478,582,2,"多选题","(2014年)关于措施项目工程量清单编制与计价，下列说法中正确的是（）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","不能计算工程量的措施项目也可以采用分部分项工程量清单方式编制",false,{"key":16,"text":17,"correct":18},"B","安全文明施工费按总价方式编制，其计算基础可为“定额基价”、“定额人工费”",true,{"key":20,"text":21,"correct":14},"C","总价措施项目清单表应列明计量单位、费率、金额等内容",{"key":23,"text":24,"correct":18},"D","除安全文明施工费外的其他总价措施项目的计算基础可为“定额人工费”",{"key":26,"text":27,"correct":14},"E","按施工方案计算的总价措施项目可以只需填“金额”数值","BD","本题考查的是措施项目清单。不能计算工程量的措施项目应该以“项”为单位报价，所以选项A错误；总价措施项目清单表应列明费率、金额等内容，不包括计量单位，所以C错误；按施工方案计算的措施费，若无“计算基础”和“费率”的数值，也可只填“金额”数值，但应在备注栏说明施工方案出处或计算方法。E错。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]