[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899456":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},899456,582,2,"多选题","(2013年)关于措施费中超高施工增加费，下列说法正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","单层建筑檐口高度超过30m时计算",false,{"key":16,"text":17,"correct":18},"B","多层建筑超过6层时计算",true,{"key":20,"text":21,"correct":18},"C","包括建筑超高引起的人工功效降低费",{"key":23,"text":24,"correct":14},"D","不包括通信联络设备的使用费",{"key":26,"text":27,"correct":18},"E","按建筑物超高部分建筑面积以“m2”为单位计算","BCE","选项A，单层建筑物檐口高度超过20m时计算超高施工增加费；选项D，包括通信联络设备的使用及摊销费。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程计价","建筑工程",0]