[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899428":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},899428,582,1,"单选题","（2016年考题）根据《建设项目工程总承包合同示范文本》（GB-2011-0216），下列变更事项中属于设计变更的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基准控制点的调整",true,{"key":16,"text":17,"correct":18},"B","备品备件采购数量的调整",false,{"key":20,"text":21,"correct":18},"C","新增加的施工障碍处理",{"key":23,"text":24,"correct":18},"D","增加的附加试验","本体考察的是工程中承包合同价款的结算。选项B属于采购变更；选项CD属于施工变更；",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]