[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899427":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},899427,582,1,"单选题","（2017年考题）根据《建设项目工程总成本合同示范文本（试行）》（GF-2011-0216），下列变更事项，属于采购变更的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对设备规格和数量的调整",false,{"key":16,"text":17,"correct":18},"B","改变检查、检验、检测、试验地点",true,{"key":20,"text":21,"correct":14},"C","重新进行竣工试验",{"key":23,"text":24,"correct":14},"D","对配套工程系统的工艺调整","采购变更。采购变更的范围包括:①承包人已按合同约定的程序，与相关供货商签订采购合同或已开始加工制造、供货、运输等，发包人通知承包人选择另一家供货商；②因执行基准日期之后新颁布的法律、标准、规范引起的变更；③发包人要求改变检查、检验、检测、试验的地点和增加的附加试验；④发包人要求增减合同中约定的备品备件、专用工具、竣工后试验物资的采购数量；⑤上述变更所需的附加工作。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]