[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899422":3},{"question":4,"library":22},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":21},899422,582,1,"单选题","（2019年考题）关于合同价款的期中支付，下列说法正确的是（ ）。 A.进度款支付周期应与发包人实际的工程计量周期一致 B.已标价工程量清单中单价项目结算价款应按承包人确认的工程量计算C承包人现场签证金额不应列入期中支付进度款，在竣工结算时一并处理 D.进度款的支付按期中结算价款总额和约定比例计算，一般不低于60%，不高于90%",[11,14,16,18],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":13},"C",{"key":19,"text":19,"correct":20},"D",true,"A错误，进度款支付周期，应与合同约定的工程计量周期一致。B错误，已标价工程量清单中的单价项目，承包人应按工程计量确认的工程量与综合单价计算，如综合单价发生调整的，以发承包双方确认调整的综合单价计算进度款。C错误，承包人现场签证和得到发包人确认的索赔金额列入本周期应增加的金额中，列入期中支付进度款。",{"id":6,"name":23,"category":24,"favorite":25},"建设工程计价","建筑工程",0]