[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899415":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},899415,582,1,"单选题","（2018年考题）因不可抗力解除合同的，发包人不应向承包人支付的费用是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","临时工程拆除费",false,{"key":16,"text":17,"correct":18},"B","承包人未交付材料的货款",true,{"key":20,"text":21,"correct":14},"C","已实施的措施项目应付价款",{"key":23,"text":24,"correct":14},"D","承包人施工设备运离现场的费用","发包人除应向承包人支付合同解除之日前已完成工程但尚未支付的合同价款，还应支付下列金额：（1）合同中约定应由发包人承担的费用。（2）已实施或部分实施的措施项目应付价款。（3）承包人为合同工程合理订购且已交付的材料和工程设备货款。发包人一经支付此项货款，该材料和工程设备即成为发包人的财产。（4）承包人撤离现场所需的合理费用，包括员工遣送费和临时工程拆除、施工设备运离现场的费用。（5）承包人为完成合同工程而预期开支的任何合理费用，且该项费用未包括在本款其他各项费用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]