[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899414":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},899414,582,1,"单选题","（2020年真题）承包人按合同接受竣工结算支付证书的，可以认为承包人已无权要求（ ）颁发前发生的工程变更。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同工程接纳证书",true,{"key":16,"text":17,"correct":18},"B","质量保证金返还证书",false,{"key":20,"text":21,"correct":18},"C","缺陷责任期终止证书",{"key":23,"text":24,"correct":18},"D","最终支付证书","P263 承包人按合同约定接受了竣工结算支付证书后，应被认为已无权再提出在合同工程接收证书颁发前所发生的任何索赔。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]