[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899411":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899411,582,1,"单选题","（2020年真题）发生下列工程事项时，发包人应予计量的是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人自行增建的临时工程工程量",false,{"key":16,"text":17,"correct":14},"B","因监理人抽查不合格返工增加的工程量",{"key":19,"text":20,"correct":21},"C","承包人修复因不可抗力损坏工程增加的工程量",true,{"key":23,"text":24,"correct":14},"D","承包人自检不合格返工增加的工程量","P254-256 工程计量的原则包括下列三个方面：（1）不符合合同文件要求的工程不予计量。（2）按合同文件所规定的方法、范围、内容和单位计量。（3）因承包人原因造成的超出合同工程范围施工或返工的工程量，发包人不予计量。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]