[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899404":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899404,582,1,"单选题","（2017年考题）调解是解决工程合同价款纠纷的一种途径，下列关于调解的说法中正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人对调解书有异议的，可以停止施工",false,{"key":16,"text":17,"correct":14},"B","发承包双方签字认可的调解书不能作为合同的补充文件",{"key":19,"text":20,"correct":21},"C","发承包双方可在合同履行期间协议调换或终止合同约定的调解人",true,{"key":23,"text":24,"correct":14},"D","调解人的任期在竣工结算经发承包双方确认时终止","合同履行期间，发承包双方可以协议调换或终止任何调解人，但发包人或承包人都不能单独采取行动。除非双方另有协议，在最终结清支付证书生效后，调解人的任期即终止。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]