[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899402":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899402,582,1,"单选题","（2016年考题）已知某建筑工程施工合同总额为8000万元，工程预付款按合同金额的20%计取，主要材料及构件造价占合同额的50%。预付款起扣点为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1600",false,{"key":16,"text":17,"correct":14},"B","4000",{"key":19,"text":20,"correct":21},"C","4800",true,{"key":23,"text":24,"correct":14},"D","6400","本题考查的是预付款及期中支付。起扣点的累计完成工程金额=承包工程合同总额-工程预付款总额\u002F主要材料及构件所占比重=8000-8000×20%\u002F50%=4800万元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]