[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899395":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},899395,582,1,"单选题","（2017年考题）根据《建设工程工程量清单计价规范》（GB50500-2013），关于工程计量，下列说法中正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同文件中规定的各种费用支付项目应予计量",true,{"key":16,"text":17,"correct":18},"B","因异常恶劣天气造成的返工工程量不予计量",false,{"key":20,"text":21,"correct":18},"C","成本加酬金合同应按照总价合同的计量规定进行计量",{"key":23,"text":24,"correct":18},"D","总价合同应按实际完成的工程量计算","成本加酬金合同按照单价合同的计量规定进行计量；采用工程量清单方式招标形成的总价合同，工程量应按照与单价合同相同的方式计算。采用经审定批准的施工图纸及其预算方式发包形成的总价合同，除按照工程变更规定引起的工程量增减外，总价合同各项目的工程量是承包人用于结算的最终工程量。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]