[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899390":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},899390,582,1,"单选题","（2017年考题）关于施工合同价款的期中支付，下列说法中正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","期中进度款的支付比例，一般不低于期中价款总额的60%",true,{"key":16,"text":17,"correct":18},"B","期中进度款的支付比例，一般不高于期中价款总额的80%",false,{"key":20,"text":21,"correct":18},"C","综合单价发生调整的项目，其增减费在竣工结算时一并结算",{"key":23,"text":24,"correct":18},"D","发承包双方如对部分计算量结果存在争议，等待争议解决后在支付全部进度款","B选项不高于90%；C选项应在本期结算；D选项若发、承包双方对有的清单项目的计量结果出现争议，发包人应对无争议部分的工程计量结果向承包人出具进度款支付证书。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]