[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899386":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},899386,582,1,"单选题","（2018年考题）某施工合同中的工程内容由主体工程与附属工程两部分组成，两部分工程的合同额分别为800万元知200万元。合同中对误期赔偿费的约定是：每延误一个日历天应赔偿2万元，且总赔费不超过合同总价款的5%，该工程主体工程按期通过竣工验收，附属工程延误30日历天后通过竣工验收，则该工程的误期赔偿费为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1O",true,{"key":16,"text":17,"correct":18},"B","12",false,{"key":20,"text":21,"correct":18},"C","50",{"key":23,"text":24,"correct":18},"D","6","本题考查的是工程索赔类合同价款调整事项。附属工程延误30日历天应赔偿30××2=60（万元），总赔费最高=（800+200）×5%=50（万元）。而主体工程按期通过竣工验收，误期补偿费应按比例扣减，则该工程的误期赔偿费=50-800\u002F1000×50=10（万元）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]