[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899380":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},899380,582,1,"单选题","（2019年考题）.下列发承包双方在约定调整合同价款的事项中属于工程变更的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程量清单缺项",true,{"key":16,"text":17,"correct":18},"B","不可抗力",false,{"key":20,"text":21,"correct":18},"C","物价波动",{"key":23,"text":24,"correct":18},"D","提前竣工","工程变更类，主要包括工程变更、项目特征不符、工程量清单缺项、工程量偏差、计日工等享件。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]