[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899379":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899379,582,1,"单选题","（2019年考题）某招标工程项目执行《建设工程工程量清单计价规范》（GB50500-2013）,招标工程量清单中某分项工程的工程量为1500m3，施工中由于设计变更调增1900m3,该分项工程最高投标限价综合单价为40元\u002Fm3,投标报价为47元\u002Fm3,则该分项工程的结算价为（ ）元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","87400",false,{"key":16,"text":17,"correct":14},"B","88900",{"key":19,"text":20,"correct":21},"C","89125",true,{"key":23,"text":24,"correct":14},"D","89300","1900\u002F1500=127%，工程量增加超过15%，40×（1+15%）=46\u003C47，超过15%的工程量按46元结算，1500×1.15×47+（1900-1500×1.15）×46=89125元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]