[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899377":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},899377,582,1,"单选题","（2019年考题）根据《标准施工招标文件》（2007年版）通用合同条款，下列引起承包人索赔的事件中，可以同时获得工期、费用和利润补偿的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工中发现文物、古迹",false,{"key":16,"text":17,"correct":18},"B","发包人延迟提供建筑材料",true,{"key":20,"text":21,"correct":14},"C","承包人提前竣工",{"key":23,"text":24,"correct":14},"D","因不可抗力造成工期延误","A选项只能获得工期、费用补偿；C选项只能获得费用补偿；D选只项能获得工期补偿。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]