[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899374":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899374,582,1,"单选题","（2020年真题）因工程变更引起措施项目发生变化时，关于合同价款的调整，下列说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","安全文明施工费不予调整",false,{"key":16,"text":17,"correct":14},"B","按总价计算的措施项目费的调整，不考虑承包人报价浮动因素",{"key":19,"text":20,"correct":21},"C","按单价计算的措施项目费的调整，以实际发生变化的措施项目数量为准",true,{"key":23,"text":24,"correct":14},"D","招标清单中漏项的措施项目费的调整，以承包人自行拟定的实施方案为准","P237-241 A选项:安全文明施工费，按照实际发生变化的措施项目调整，不得浮动; B选项:按总价（或系数）计算的措施项目费，除安全文明施工费外，按照实际发生变化的措施项目调整，但应考虑承包人报价浮动因素; D选项:由于招标工程量清单中措施项目缺项，承包人应将新增措施项目实施方案提交发包人批准后，按照工程变更事件中的有关规定调整合同价款。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]