[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899370":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},899370,582,1,"单选题","（2020年真题）根据现行《建设工程工程量清单计价规范》，对于不实行招标的建设工程，建设工程施工合同签订前的第（）天作为基准日。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","28",true,{"key":16,"text":17,"correct":18},"B","30",false,{"key":20,"text":21,"correct":18},"C","35",{"key":23,"text":24,"correct":18},"D","42","P236-237 对于不实行招标的建设工程，一般以建设工程施工合同签订前的第28天作为基准日。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]