[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899369":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},899369,582,1,"单选题","（2020年真题）施工合同履行期间出现现场签证事件时，现场签证应由（）提出。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":14},"B","监理人",{"key":19,"text":20,"correct":14},"C","设计人",{"key":22,"text":23,"correct":24},"D","承包人",true,"P253-254 承包人应发包人要求完成合同以外的零星项目、非承包人责任事件等工作的，发包人应及时以书面形式向承包人发出指令，提供所需的相关资料;承包人在收到指令后，应及时向发包人提出现场签证要求。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]