[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899367":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},899367,582,1,"单选题","（2017年考题）根据《建设工程工程量清单计价规范》（GB50500-2013），中标人报价浮动率的计算公式是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","（1-中标价\u002F招标控制价）×100%",false,{"key":16,"text":17,"correct":14},"B","（1-中标价\u002F施工图预算）×100%",{"key":19,"text":20,"correct":21},"C","（1-不含安全文明施工费的中标价\u002F不含安全文明施工费的招标控制价）×100%",true,{"key":23,"text":24,"correct":14},"D","（1-不含安全文明施工费的中标价\u002F不含安全文明施工费的施工图预算）×100%","招标工程：报价浮动率=（1-中标价\u002F招标控制价）×100%；中标价、招标控制价均不含安全文明施工费。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]