[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-899357":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},899357,582,1,"单选题","（2017年考题）关于施工合同履行过程中共同延误的处理原则，下列说法中正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在初始延误发生作用期间，其他并发延误者按比例承担责任",false,{"key":16,"text":17,"correct":18},"B","若初始延误者是发包人，则在其延误期内，承包人可得到经济补偿",true,{"key":20,"text":21,"correct":14},"C","若初始延误者是客观原因，则在其延误期内，承包人不能得到经济补偿",{"key":23,"text":24,"correct":14},"D","若初始延误者是承包人，则在其延误期内，承包人只能得到工期补偿","C选项，若果初始延误者是客观原因，则在客观因素发生影响的延误期内，承包人可以得到工期延长，但很难得到费用补偿；D选项，如果初始延误者是承包人原因，则在承包人原因造成的延误期内，承包人既不能得到工期补偿，也不能得到费用补偿。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程计价","建筑工程",0]